Stony Brook University Campus Wide Mechanical And Electrical Building Infrastructure Upgrades Projects
Construction Manager for a Campus Wide HVAC modernization of 11 buildings including replacement of existing BMS control system. Modernization of the Lab Control and HVAC system within 256 labs. Scope included modifications to the supply, exhaust and fume hood exhaust systems, installation of a fully operational BMS system, installation of an Aircuity air quality control system, relocate and replace building reheat coils, retro-commissioning of existing systems to integrate with new controls, plus sealing all building ductwork. Project also include replacing in excess of 30,000 existing lighting fixtures in all Residence Hall Buildings with LED equivalent.
Given the existing conditions of research and teaching labs, the project required a significant amount of coordination for the construction phase. The project was bid under multiple bid packages with Guth DeConzo directly managing eleven subcontractors and material/equipment suppliers. The project was completed in Fall, 2021 with a total construction duration of 140 weeks.
Project Details
Client:
State University of New York
at Stony Brook
Location:
Stony Brook, NY
Contract Value:
$68,200,000
Guth DeConzo Role:
Construction Manager/Engineer of Record
Project Engineer:
Guth DeConzo Consulting Engineers
Major Subcontractor/Suppliers:
- Walsh Construction
- Boilermatic Welding Industries
- KND Electric
- HVAC NY, Inc.
- Siemens
Project Status and Schedule:
Completed December, 2021