Project Description:

Design Build Manager for the installation of 230 overhead pantograph bus charging systems at six NYCT bus depot locations throughout the Metro NYC area. Project is being implemented in a fast track format utilizing multiple Design-Build Teams, ABB and Heliox charging equipment technology and INIT Charge Management Software. Work is to taking place within the following existing bus depots with strict logistical restrictions:

  • Gun Hill Bus Depot – 60 pantographs
  • Mother Clara Hale Bus Depot – 34 pantographs
  • Grand Avenue Bus Depot – 44 pantographs
  • Queens Village Bus Depots – 60 pantographs
  • Herkimer/East New York Bus Depot – 22 pantographs
  • M.J. Quill Bus Depot – 16 cable reel chargers

Project Details

Client:
New York City Transit (NYCT)

Location:
New York, NY (Multiple Depot Locations)

Contract Value:
$190,000,000

Guth DeConzo Role:
Design Build Manager/Construction Manager

Design Consultants:

  • STV
  • MP Engineering

Major Subcontractor/Suppliers:

  • PJS Group
  • E-J Electrical Installation
  • Multi-Phase Electric
  • ABB, Heliox
  • Shunk
  • Stemmann

Project Status and Schedule:
In Construction. Scheduled Completion – January, 2026