New York City Transit eBus Charging Infrastructure Project – Phase 1
Design and installation of 28 overhead pantograph bus charging infrastructure system at four NYCT locations – East New York, Herkimer, Kingsbridge, and Williamsburg – utilizing Siemens and ABB systems. Project requires extensive electrical service upgrades as well as new feeder installation. Includes Electrical Distribution Equipment, Charger Branch Circuits, Overhead Charging systems, and associated structural steel gantry components. Work is to take place within existing bus depots with strict logistical restrictions.
Project Details
Client:
New York City Transit
Location:
New York, NY
Contract Value:
$28,000,000
Guth DeConzo Role:
Construction Manager
Project Engineer:
Guth DeConzo Consulting Engineers
Major Subcontractor/Suppliers:
- PJS Electric
- E-J Electric
- ABB
- Siemens
Project Status and Schedule:
Design phase completed and construction is ongoing. Construction completion scheduled for December 2023